Summary: Activity Based Costing in Construction
Dear Travis, Glen et al,
Here is how we in construction use ABC.
Step 1- We either purchase or develop a cost estimating database which is DELIVERABLE or SYSTEM based. In the example below, I have used Cubic Yards of Concrete, (Unit Pricing) from RS Means Facilities Cost book, http://www.rsmeans.com/bookstore/detail.asp?sku=60209 but I could have also used an [...]
Dear Travis, Glen et al, Here is how we in construction use ABC.
Step 1- We either purchase or develop a cost estimating database
which is DELIVERABLE or SYSTEM based. In the example below, I have
used Cubic Yards of Concrete, (Unit Pricing) from RS Means
Facilities Cost book,
http://www.rsmeans.com/bookstore/detail.asp?sku=60209 but I could
have also used an [...]